BC Hydro Maintenance

BC Hydro Maintenance

Client: BC Hydro

Owner: BC Hydro

Project Status: Completed

Location: Anahim Lake & Nimpo Lake BC

Voltage: 25kV

Category: Distribution

The Project: This Project consisted of the replacement of old porcelain cutouts and associated hardware.  Aging porcelain cutouts are prone to failure and a replacement program was implemented to increase system reliability.

 

Challenges: The winter conditions resulted in decreased access, forcing crews to hike or snowmobile into many sites and climb poles to complete the work for which they would normally use a bucket truck to access.